FIFA lead regional development officer David Fani has expressed concern that the newly rehabilitated Kasama Sports Stadium has already begun to deteriorate due to poor maintenance and prolonged non-usage, despite a substantial investment intended to revive the facility. During an inspection of the stadium on Wednesday, Fani noted that although the contractor had officially handed over the project, several tasks still needed to be completed before the stadium can become fully operational. “We took note of the fact that most of the works have actually been done (according to the scope of works), that there was actually a technical handover of the project from the contractor to us. We acknowledge that there are some few works that need to be...