THE Public Accounts Committee (PAC) has heard that the Ministry of Fisheries and Livestock continued to use an expired contract and paid K1,631,884 for the construction of a livestock slaughter facility in Kasama District which remains incomplete, 55 months after construction deadline. On September 20, 2016, the Ministry of Fisheries and Livestock signed a contract with Lamasat International Limited for the construction of a livestock slaughter facility in Kasama District of Northern Province at a contract sum of K2,070,035 VAT exclusive with a delivery period of 18 weeks commencing October 27, 2016 to March 15, 2017. And Ministry of Fisheries and Livestock Head of Procurement Clement Mukuka says the Office of the Attorney General was not engaged for guidance after...